Green and black, and blue and white

Sometimes you have to look up as well as down.

Here are some of Zeke’s favorite roadside foods.

greenblackberries

They’re a little blurred, which I will blame on Zeke and Sam pulling on me while I tried to take a picture. These are unripe blackberries. Zeke checked them but they were too green even for him. This was Tuesday evening.

On Wednesday, we looked up instead of down.

clouds1

There were lots of cirrus unchains (this is a link to a source other than Wikipedia, for a change), or mare’s tail clouds. They were changing very quickly, even as we walked along the road. When we got home I saw these from our back deck.

clouds2

They were slowly fading to pink. I sat for a few minutes, but the sky was changing so quickly that they were gone before the setting sun could paint them.

The sky on Wednesday seemed particularly beautiful to me because we had some good news earlier in the day. A second flooring contractor came out and measured for tile and hardwood. He sounded knowledgeable, even about electrically-heated bathroom floors. He gave a reasonable estimate for the work, less than I had expected. And, what’s more, he said he could almost certainly start by May 23. That will work out almost perfectly, because I hope the interior painting will be done by then, and, maybe, just maybe, the power and heating/AC as well. The timing was very good, although it’s clear at this point that we will not be in the house by the end of May. However, I am willing to bet (a small amount) that we can be ready to move in by the end of June, assuming our buyers’ bank is able to move reasonably quickly. It even seems that I will be able to do the trim work in the new house.

I’m pretty happy about things right now, but don’t tell Fate about that.

 

House progress

I have finally made some progress on finishing the basement of our current house. I took this shot a few days ago.

basement floor

I used the blue masking tape to make sure joints didn’t separate when I was snapping a new piece of flooring into place. Since then I have completed the flooring in the den. That leaves the flooring in the downstairs bedroom closet, which should take only a short time. Then it’s hanging doors and installing baseboards, and the basement will be essentially finished. Of course I still have to replace some cracked tiles in the master bathroom.

We are also approaching completion of drywall in the new house. The drywall contractor has been taping and mudding. He expects to be done by the end of the week.

The interior of the house looks like an actual house now. I expected to see it differently at this point, but I think I have been visualizing it so much that I already knew what it was going to look like.

Attic insulation comes next; that is tentatively scheduled with a helper for this Saturday. I have to do a little more in the attic and then I’m ready. The only thing standing in the way is a decision about whether to use blow-in cellulose or blow-in fiberglass. The biggest disadvantage to cellulose, other than the big mess it leaves, is that it will take at least 135 bags, while the fiberglass will take only about 50. I think I can get 50 bags on my truck and trailer, but not 135 bags. The big-box store gives a free one-day rental of the blowing machine if you buy enough bags of insulation (I’ll meet that requirement several times over), but it might well take more than one day to blow in the cellulose. I’ll have to make a decision on that in the next couple of days.

I saw my doctor on Tuesday about my right shoulder, which I injured in a fall in the new garage. (Step ladders were invented by the devil.) When I first injured it, it seemed to be a minor inconvenience. After a week or two, it was a major inconvenience. I couldn’t lift my right arm high enough to brush my hair, and I had to use my left hand to help my right hand reach the steering wheel when I drove. But Sunday I surprised myself by being able to raise my right arm over my head without any significant pain. I was pretty sure it was a torn rotator cuff, but the doctor is not certain. Leah suggested earlier that it might not be. The doctor ordered an X-ray to make sure the shoulder is not dislocated, and some ibuprofen to help with any inflammation. No visit to the orthopedic surgeon yet, and possibly not at all. And it seems that I can use my right arm for some things if I’m careful.

Like unloading about a half a ton of floor tile for the new house.

tiledelivery

I’m supposed to meet a flooring contractor Wednesday morning to get an estimate for tile and hardwood. The contractor I had originally intended to use says he is booked through June, and that just won’t work.

My forecast is for completion of attic insulation this weekend, and the start of painting early next week. Some time during the weekend I hope to install the final exterior door so the house can be locked, and after that, to get electrical power inside the house. Then it’s a clear path to an air conditioned house and hardwood flooring. And, if my right shoulder behaves itself, I may be able to install the interior doors and do the trim work myself.

Drywall in the bedroom

The drywall contractor started work on Tuesday. I went up Tuesday morning to point out a few places they needed to leave wiring exposed (bathroom floor heat thermostat wires, garage door opener wires, and wiring for under-cabinet lights in the kitchen). I thought they might start in the garage, but they were working in our bedroom.

bedroomdrywall

As you can see, they put the drywall in right over the top of the windows. They come back later with little router-type tools to cut the excess away. They have hidden the top part of the window where we have equal-leg arches. Framing around those was one of the things I wanted to do before they started, but now I think I’m going to have to frame and trim them out later. I have some ideas about how to do it. It will be interesting to see how well the ideas translate into reality.

Here’s Leah standing in the door to the bathroom.

drywallstart

She said the bedroom looked smaller with drywall up. I think that’s to be expected. I have noticed that the appearance of a house bounces back and forth between small and large, depending on the state of construction (or which pill you have taken).

We finally picked out hardwood. It’s going to be a fairly dark, reddish, cherry-stained oak. We worried about getting the floors too dark. Neighbor John and his wife used very dark flooring for their new house down Wildlife Trail from us. We didn’t want it quite that dark. I think it will work out. We also found some wood-look tile that matches the flooring very well. We’ll use that in the kitchen and the bathrooms. I’ll probably buy the the tile in the next few days, since I can store it in our current garage. I’ll have to wait on the hardwood until we have a working heating/air conditioning system in the new house, since hardwood needs to acclimate to its future environment.

The drywall contractor estimated it will take a week or so to finish. I’ll call the tile installer in the next few days to let him know when the drywall should be finished, and then we’ll have to hurry to paint before he starts. He’s a pretty busy guy, so we may not have to hurry that much. I hope he knows a good hardwood floor installer. I also have to contact the electrician. Once the drywall is all in, the electrician can hook up some outlets to the breaker panel. Then the power company can install our meter and hook us up to power. Then the HVAC contractor can finish up his work, and we’ll have a cool house.

Then all we need to do is work on our own coolness.

Drywall delivery

The drywall installer called on Monday and asked if he could have drywall delivered Tuesday. Of course I said of course, even though the house was too messy for them to deliver. They distribute drywall throughout the house so the installer doesn’t have to move it so far, so the floors need to be clear of construction material and debris. That meant I spent the rest of the day Monday and the morning on Tuesday clearing lumber from the garage and various insulation-related stuff from the house.

Here’s the first load going into the garage.

unloading in the garagr

The truck has a long boom that picks up a stack of drywall and swings it around right to the door.

Neither the delivery guys nor the installers like to lug drywall up stairs, so they try to unload directly into each level of a house. Our floor is three steps up from the garage, so they used a bedroom window.

swinging drywall

Our windows are double-hung, and made so that each sash comes completely out.

We (or the drywall people) are lucky I wanted deep windows in our bedroom. If you look at the closer window below, you can probably tell that it isn’t tall enough to unload drywall through. Our bedroom window is just tall enough.

into the window

The drywall just fits. Here is one of the delivery guys taking a few sheets into the bedroom.

unloading in the bedroom

At the extreme right of the photo you can see a little of the flexible silver duct the heating and AC contractor installed Monday. It will be used to blow warm air from the wood-burning stove in the living room to our bedroom.

I spent the rest of the day Tuesday building a small chase to hide that duct. In addition to that, I need to insulate a few more stud bays and put up my attic insulation measuring sticks. I cut about 80 20-inch long pieces of 2×4 to nail to the ceiling joists as depth indicators. I ripped them on my table saw at home right after lunch. During that process I did not cut off any body parts, but I did stick my left index finger into the spinning blade. It bled (not as much as I expected, being on a daily aspirin). I hurried inside, a little afraid to wash it and see how much damage I did. It chewed out a small bit of flesh and a little of the tip of the nail. It doesn’t hurt to speak of, which suggests to me that it got just enough of the tip of the finger to destroy the nerve endings. I think I’ll end up with a little scar there. And, of course, I’m finding out just how many times you use the letters f, g, t, r, c, and v when you type.

The delivery guys distributed the drywall to various places in the house, ready for the installer to start work. I expected to be ready for him by the weekend, but now I think it will probably be Thursday before I call him.

Inspection passed!

The building inspector came back for a re-inspection on Tuesday. We passed.

He basically took my word for everything that wasn’t easily visible, like the framing repairs. He had noted several plumbing issues, which I told him had been corrected. He suggested that we add some metal tie straps to the side framing of the garage doors, to help prevent the garage from blowing away in a strong wind (assuming we had left the garage doors open, which we won’t). We needed four angle brackets specially designed for that purpose at a cost of $20 each. That’s a lot for metal brackets, but not so much in the context of a cost of the whole house.

I bought the brackets and spent an hour and a half drilling holes in the concrete pad of the garage, installing concrete anchors and bolts, and hammering 25 nails into each bracket.

The inspector said we can start drywalling. The drywall contractor said he can start pretty much when I call. Several things have to be done first. I have to complete the insulation, which I think I can do in a couple of days, or one if I’m really diligent. On second thought, make that two days. The heating and air-conditioning contractor is going to install a duct we’ll use to blow warm air from the wood-burning stove back into our bedroom. That should happen this week. The chimney man will install all the wood stove fittings from the ceiling through the cap on the chimney. That should happen early next week. I want to install a walkway in the attic that will give us access to the whole-house fan and the warm-air blower when the attic insulation is done. That should happen by the end of the weekend.

And then drywall. And then paint. And then electricity. And then the heating/air conditioning contractor can complete the HVAC system. That will allow us to condition the air in the house, which will allow our wood flooring to get used to the conditions that it will experience when we move in. And then wood floors in the living room, hall, and bedrooms, and maybe kitchen. And tile in the bathrooms, and maybe the kitchen. There are several things that may have lead times of several weeks, so we need to pick them out now and possibly order them within a week or so. That includes wood flooring, bathroom vanities, and possibly some light fixtures.

And, of course, I have to finish up the basement in our current house, hopefully before the end of May.

We need to get busy.